Pipeline Permitting: Interstate and Intrastate Natural Gas Permitting Processes Include Multiple Steps, and Time Frames Vary

Pipeline Permitting: Interstate and Intrastate Natural Gas Permitting Processes Include Multiple Steps, and Time Frames Vary

Full Title: Pipeline Permitting: Interstate and Intrastate Natural Gas Permitting Processes Include Multiple Steps, and Time Frames Vary
Author(s): U.S. Government Accountability Office
Publisher(s): U.S. Government Accountability Office
Publication Date: February 1, 2013
Full Text: Download Resource
Description (excerpt):

Both the interstate and intrastate natural gas pipeline permitting processes are complex and can involve multiple federal, state, and local agencies, as well as public interest groups and citizens, and include multiple steps. The interstate process involves a voluntary pre-filing phase, an application phase, and a post-authorization phase with multiple steps that stakeholders reported to be consistent among projects because the process is led by the Federal Energy Regulatory Commission (FERC). FERC coordinates with federal, state, and local agencies that have statutory and regulatory authority over various environmental laws and regulations. For example, if a proposed pipeline may affect endangered species, FERC coordinates with the U.S. Fish and Wildlife Service, which reviews the impacts on such species. The intrastate process can also involve multiple stakeholders and steps, but, unlike in the interstate process, GAO found that the stakeholders and steps vary by state. For example, of the 11 states GAO reviewed, 5 have agencies charged with approving the route of natural gas pipelines and require advance approval of the location and route, and the remaining 6 do not. Pipeline companies must also comply with various federal and state environmental laws and regulations; however, in most of the 11 states, no one agency is charged with coordinating the implementation of these laws and regulations as FERC is for the interstate process.

Time frames associated with the interstate and intrastate permitting processes vary because of multiple factors, according to stakeholders. For the interstate process, FERC does not track time frames, citing the limited usefulness of such data. GAO analyzed public records and found that, for those projects that were approved from January 2010 to October 2012, the average time from pre-filing to certification was 558 days; the average time for those projects that began at the application phase was 225 days. For the intrastate process, because processes vary by state, the time frames of those processes may also vary. GAO found little comprehensive data on the intrastate process. According to GAO’s discussions with stakeholders, several factors can affect the time frame for the permitting process of a given project, including different types of federal permits or authorizations, delays in the reviews needed by governmental stakeholders, and incomplete applications. For example, state and local permitting and review processes can affect federal decision-making time frames because some federal agencies will not issue their permits until state and local governments have completed their own permitting processes, according to some stakeholders.

Officials from federal and state agencies and representatives from industry and public interest groups told GAO that several management practices could help overcome challenges they associated with an efficient permitting process and obtaining public input: (1) ensure a lead agency is coordinating the efforts of federal, state, and local permitting processes for intrastate pipelines, (2) ensure effective collaboration of the numerous stakeholders involved in the permitting process, (3) provide planning tools to assist companies in routing pipelines and avoiding sensitive environmental resources, (4) offer industry the option to fund contractors or agency staff to expedite the permitting process, and (5) increase the opportunities for public comments.

All statements and/or propositions in discussion prompts are meant exclusively to stimulate discussion and do not represent the views of OurEnergyPolicy.org, its Partners, Topic Directors or Experts, nor of any individual or organization. Comments by and opinions of Expert participants are their own.

Sign up for our Press Release Distribution List

    Your Name (required)

    Your Email (required)

    Please sign me up to receive press releases from OurEnergyPolicy.org.